Taijiang Boulevard is Tainan City Class-2 Road No. 7 (Road 2-7), running from Anji Road in the east to the Qingcaolun Seawall in the west, about 13.8 km in all; it opened in sections from 2007 onward, and the full route opened on 2017-03-12. The section behind the temple, which passes through Tucheng, broke ground in 2014 and opened in 2015, cutting the banyan grove behind the Orthodox Luermen Shengmu Temple in two (local residents' oral accounts). The route originally passed through the Shengmu Temple's sutra lecture hall; it was moved north to avoid it, shortening the full route by 800 m.
Key events
First items: Work begins on the middle section (Anji …Middle section opens to traffic (Freeway…Phase 1 of the eastern section (Anji Roa…MoreLess
- 2005
12Work begins on the middle section (Anji …MoreLess
Work begins on the middle section (Anji Road (安吉路) to Anming Road (安明路)) (blog; unverified)
- 2007
12-18Middle section opens to traffic (Freeway…MoreLess
Middle section opens to traffic (Freeway Bureau: the 「國道 8 號銜接西濱公路工程」 ("Project Connecting National Freeway No. 8 to the West Coast Highway") completed and opened)
- 2013
04-15Phase 1 of the eastern section (Anji Roa…MoreLess
Phase 1 of the eastern section (Anji Road to Anhe Road) opens to traffic06-13Work begins on Phase 1 of the western se…MoreLess
Work begins on Phase 1 of the western section (Anming Road to Chengbei Road) (Transportation Yearbook)
- 2014
03-07Phase 1 of the western section (Anming R…MoreLess
Phase 1 of the western section (Anming Road to Chengbei Road, 420 m) completed; one account gives the opening date as 2015-02-09 R009Source臺南市政府工務局 [Public Works Bureau, Tainan City Government], 《中華民國 103 年度單位決算》 [Unit Final Accounts for ROC Year 103 (2014)], general explanation, pp. 6–7Original URL—Retrieved2026-11-06Snapshot timestamp—Official final accounts, checked against the original online. General explanation, pp. 6–7: the western section of Annan District Road 2-7, "Anming Road to Chengbei Road," 420 m built, total cost NT$50 million, work began 2013-06-13 and was completed 2014-03-07. The "completed 2014-05-19" in circulation is the completion date of Annan District Road 3-71 (the Tong'an Road extension, 2,200 m) in the next paragraph on the same page, unrelated to Taijiang Boulevard. Wikipedia separately gives an opening date of 2015-02-09, from a single secondary source.Unverified07-08Groundbreaking for the section behind th…MoreLess
Groundbreaking for the section behind the temple (the works behind the Shengmu Temple) (media)
- 2015
08-04Section behind the temple (Chengbei Road…MoreLess
Section behind the temple (Chengbei Road to Qingsha Street) opens to traffic; work on Section 6 (Qingsha Street to the Qingcaolun Seawall (青草崙堤防)) begins the same day
- 2016
03-31 / 2016-05-23Phases 2 and 3 of the eastern section op…MoreLess
Phases 2 and 3 of the eastern section open, completing the eastern section
- 2017
03-12Ceremony for the opening of the full rou…MoreLess
Ceremony for the opening of the full route, combined with Arbor Day, at the intersection behind the temple
The section behind the temple
Ground was broken for the 「正統鹿耳門聖母廟後方工程」 ("works behind the Orthodox Luermen Shengmu Temple") on 2014-07-08, and the section from Chengbei Road (城北路) to Qingsha Street (青砂街) opened to traffic on 2015-08-04; it was between these two dates that the banyan grove behind the Shengmu Temple (聖母廟) was cut in two. On 2017-03-12, the ceremony for the opening of the full route, combined with Arbor Day activities, was held at the intersection of the west side of Taijiang Boulevard Section 5 (台江大道五段) and Qingsha Street, which is the intersection right behind the temple. The route originally passed through the Shengmu Temple's sutra lecture hall; it was later moved north to avoid it, and the full route was shortened by 800 m as a result. Today, every Lantern Festival (元宵), this section behind the temple, from Chengbei Road to Qingsha Street, is closed for the whole day, and the fireworks are launched from the open ground on the north side of the road.
Controversies
After the middle section opened at the end of 2007, the road embankment of Section C001, filled with converter slag, made the road surface heave in waves; on 2009-11-11 the Control Yuan censured the Taiwan Area National Expressway Engineering Bureau, and in August 2011 prosecutors indicted Lai Tai-wen (賴泰文), the head of the contractor Yiching Construction (亦慶營造); accounts of the amount of unlawful gain differ (about NT$30 million to NT$38 million) R010Source監察院 [Control Yuan] press release, 〈國道八號銜接台十七線西濱公路之台江大道,因不當使用轉爐石填築路堤,導致路面隆起呈波浪狀……糾正交通部臺灣區國道新建工程局〉 ["Taijiang Boulevard, which connects National Freeway No. 8 to the Provincial Highway 17 West Coast Highway, improperly used converter slag to fill the embankment, causing the road surface to heave in waves . . . Censure of the Taiwan Area National Expressway Engineering Bureau, Ministry of Transportation and Communications"] (2009-11-11); 自由時報 [Liberty Times], 〈《偷工減料》「波浪」台江大道 包商起訴〉 ["Cutting Corners: The 'Wavy' Taijiang Boulevard; Contractor Indicted"] (Huang Po-lang (黃博郎), 2011-08-03)Original URLhttps://www.cy.gov.tw/News_Content.aspx?n=124&sms=8912&s=4866Retrieved2026-11-06Snapshot timestamp—Official press release and media report, checked online.. See Taijiang Boulevard converter slag case.
Where the sources disagree
Opening date of the section behind the temple (Chengbei Road to Qingsha Street): August 3 or August 4
- Account 12015-08-04: the yam News report on the opening ceremony and the Liberty Times; the main text of Wikipedia agrees.R006Source蕃新聞 [yam News] / 今日大話新聞 [Today's Big Talk News], 〈台江大道5段(安明路至青砂街)通車典禮〉[Opening Ceremony for Section 5 of Taijiang Boulevard (Anming Road to Qingsha Street)] (2015-08-04; the section from Chengbei Road to Qingsha Street opened, and work on Section 6, from Qingsha Street to the Qingcaolun Seawall, began the same day); 自由時報 [Liberty Times], 〈2-7號道路西段工程安明路至青草崙堤防通車效益〉[Benefits of Opening the Western Section of Road 2-7 from Anming Road to the Qingcaolun Seawall]Original URLhttps://n.yam.com/Article/20150804192601Retrieved2026-10-27Snapshot timestamp—Reports from two media outlets. See also Liberty Times: https://features.ltn.com.tw/english/article/paper/904082 .
- Account 22015-08-03: the China Daily News headline cited in the Wikipedia references, 「今通車」 ("opens to traffic today").R002Source自由時報 [Liberty Times], 〈〈南部〉台江大道西段完工 3.12全線通車〉[(South) Western Section of Taijiang Boulevard Completed; Full Route Opens March 12] (2017-02; the eastern section opened in stages on 2013-04-15, 2016-03-31 and 2016-05-23; full route 13.8 km); 維基百科 [Wikipedia], 〈台江大道〉[Taijiang Boulevard]Original URLhttps://news.ltn.com.tw/news/local/paper/1081304Retrieved2026-10-27Snapshot timestamp—Media and database; secondary sources. See also Wikipedia: https://zh.wikipedia.org/zh-tw/%E5%8F%B0%E6%B1%9F%E5%A4%A7%E9%81%93 .
The two dates differ by one day.
Month in which work on the middle section beganHandling on this site: Unverified
- Account 12005-12: the New Antarctic Transfer Station blog.R003Source新南極轉運站 [New Antarctic Transfer Station] (blog on 痞客邦 [PIXNET]), 〈台南市二等七號道路-台江大道通車〉[Tainan City Class-2 Road No. 7: Taijiang Boulevard Opens to Traffic] (work on the middle section began 2005-12)Original URLhttps://ice2006.pixnet.net/blog/posts/13253866Retrieved2026-10-27Snapshot timestamp—A blog, and the only source for the month construction began; unverified.
- Account 2The official chronology records only completion and opening on 2007-12-18, not the start of work.R001Source交通部高速公路局 [Freeway Bureau, Ministry of Transportation and Communications], 「國道新建工程局歷史專頁-國工局編年大事紀」 [Historical Page of the Taiwan Area National Expressway Engineering Bureau: Chronology of the Bureau] (the 「國道 8 號銜接西濱公路工程」 [Project Connecting National Freeway No. 8 to the West Coast Highway] was completed and opened to traffic on 2007-12-18)Original URLhttps://www.freeway.gov.tw/Publish.aspx?cnid=2989Retrieved2026-10-27Snapshot timestamp—Official source.
Completion date and opening date of Phase 1 of the western sectionHandling on this site: Unverified
- Account 1Completed 2014-03-07 (Public Works Bureau final-accounts book)R009Source臺南市政府工務局 [Public Works Bureau, Tainan City Government], 《中華民國 103 年度單位決算》 [Unit Final Accounts for ROC Year 103 (2014)], general explanation, pp. 6–7Original URL—Retrieved2026-11-06Snapshot timestamp—Official final accounts, checked against the original online. General explanation, pp. 6–7: the western section of Annan District Road 2-7, "Anming Road to Chengbei Road," 420 m built, total cost NT$50 million, work began 2013-06-13 and was completed 2014-03-07. The "completed 2014-05-19" in circulation is the completion date of Annan District Road 3-71 (the Tong'an Road extension, 2,200 m) in the next paragraph on the same page, unrelated to Taijiang Boulevard. Wikipedia separately gives an opening date of 2015-02-09, from a single secondary source.
- Account 22014-05-19 (misattributed: actually the completion date of another road on the same page)R009Source臺南市政府工務局 [Public Works Bureau, Tainan City Government], 《中華民國 103 年度單位決算》 [Unit Final Accounts for ROC Year 103 (2014)], general explanation, pp. 6–7Original URL—Retrieved2026-11-06Snapshot timestamp—Official final accounts, checked against the original online. General explanation, pp. 6–7: the western section of Annan District Road 2-7, "Anming Road to Chengbei Road," 420 m built, total cost NT$50 million, work began 2013-06-13 and was completed 2014-03-07. The "completed 2014-05-19" in circulation is the completion date of Annan District Road 3-71 (the Tong'an Road extension, 2,200 m) in the next paragraph on the same page, unrelated to Taijiang Boulevard. Wikipedia separately gives an opening date of 2015-02-09, from a single secondary source.
- Account 3Opened to traffic 2015-02-09 (Wikipedia, a single secondary source)R009Source臺南市政府工務局 [Public Works Bureau, Tainan City Government], 《中華民國 103 年度單位決算》 [Unit Final Accounts for ROC Year 103 (2014)], general explanation, pp. 6–7Original URL—Retrieved2026-11-06Snapshot timestamp—Official final accounts, checked against the original online. General explanation, pp. 6–7: the western section of Annan District Road 2-7, "Anming Road to Chengbei Road," 420 m built, total cost NT$50 million, work began 2013-06-13 and was completed 2014-03-07. The "completed 2014-05-19" in circulation is the completion date of Annan District Road 3-71 (the Tong'an Road extension, 2,200 m) in the next paragraph on the same page, unrelated to Taijiang Boulevard. Wikipedia separately gives an opening date of 2015-02-09, from a single secondary source.
Correction: 2014-05-19 belongs to Annan District Road 3-71.
Place in urban planning (record in a 2014 master's thesis)
- Liu Sui-hsuan's (劉穗萱) 2014 master's thesis calls Taijiang Boulevard 「80 米寬林蔭大道二等七號道路」 ("the 80-meter-wide tree-lined boulevard, Class-2 Road No. 7"), run by the Public Works Bureau; it is an important east–west planned road of the Tainan metropolitan area and the main access road of the Tainan Technology Industrial Park, connecting with the West Coast Highway and National Freeways 8, 1 and 3 R011SourceLiu Sui-hsuan (劉穗萱),《都市邊緣區空間型態演變之研究-以台南市安南區為例》[A Study on the Spatial Transformation of Urban Fringe in Annan District of Tainan City],國立成功大學都市計劃學系 [Department of Urban Planning, National Cheng Kung University] master's thesis, 2014, pp. 47, 61–62Original URL—Retrieved2026-11-20Snapshot timestamp—SourceFrom 《A Study on the Spatial Transformation of Urban Fringe in Annan District of Tainan City (都市邊緣區空間型態演變之研究-以台南市安南區為例)》p. 47、61–62.
- Elsewhere the same thesis writes that it was 「原訂 30 米寬改為 60 米寬」 ("originally planned 30 meters wide, changed to 60 meters wide"), newly built in 2011 between Anming Road and Anhe Road across Annan District, becoming the arterial linking east and west and an outer ring connecting National Freeway 8 with the West Coast Highway R011SourceLiu Sui-hsuan (劉穗萱),《都市邊緣區空間型態演變之研究-以台南市安南區為例》[A Study on the Spatial Transformation of Urban Fringe in Annan District of Tainan City],國立成功大學都市計劃學系 [Department of Urban Planning, National Cheng Kung University] master's thesis, 2014, pp. 47, 61–62Original URL—Retrieved2026-11-20Snapshot timestamp—SourceFrom 《A Study on the Spatial Transformation of Urban Fringe in Annan District of Tainan City (都市邊緣區空間型態演變之研究-以台南市安南區為例)》p. 47、61–62. The thesis thus gives the width both as 80 and as 60 meters.
- The thesis lists the villages (里) along both sides of Class-2 Road No. 7: Donghe, Zhounan, Anshun, Xinshun, Zongtou, Budai, Yuandian, Chang'an, Xixin, Yuandong, Diandong, Yuanxi, Dianxi, Gongwen, Nanxing, Chengdong, Chengnan, Shalun and Qingcao villages R012SourceLiu Sui-hsuan (劉穗萱),《都市邊緣區空間型態演變之研究-以台南市安南區為例》[A Study on the Spatial Transformation of Urban Fringe in Annan District of Tainan City],國立成功大學都市計劃學系 [Department of Urban Planning, National Cheng Kung University] master's thesis, 2014, p. 77Original URL—Retrieved2026-11-20Snapshot timestamp—SourceFrom 《A Study on the Spatial Transformation of Urban Fringe in Annan District of Tainan City (都市邊緣區空間型態演變之研究-以台南市安南區為例)》p. 77.
See also
- Qingcaolun SeawallA seawall south of the Zengwen River mouth
- Orthodox Luermen Shengmu Temple⚖︎Mazu temple of Tuchengzi, host of the Tuchengzi Incense ProcessionContains 18 items
- Haidian RoadA major road of Annan District
- Annan District Urban PlanMain plan and detailed plans for Annan District, Tainan City
- Anming RoadThe stretch of Provincial Highway 17 in Annan District
- 1987 to present・Postwar officialsChen Pi-yuJudge on the first-instance panel in the Taijiang Boulevard police killing case
- 1987 to present・People in major eventsChen Wei-yenAn attorney in two Taijiang cases
- MoraceaeChinese banyan (Ficus microcarpa)Native tree of the mulberry family
- Heshunliao Farm zone expropriation (和順寮農場區段徵收)Development of Taisugar's Heshunliao Farm through zone expropriation
- 1987 to present・Shops and businessesLai Tai-wenHead of Yi-Ching Construction
- 1987 to present・People in major eventsLin Hsin-wuDefendant in the Taijiang Boulevard police killings
- Provincial Highway 61The West Coast Expressway
- Qingsha StreetStreet linking Tucheng, Shalun and Qingcao
- The Taijiang Boulevard Converter Slag CaseThe case of converter slag in the Taijiang Boulevard embankment
- 1987 to present・Postwar officialsTsai Ching-hsiangFormer Minister of Justice
- 1987 to present・People in major eventsTsao Jui-chiehMinquan Substation officer killed on Taijiang Boulevard
- 1987 to present・Postwar officialsTseng Chao-kaiProsecutor, Tainan Branch of the Taiwan High Prosecutors Office
- 1987 to present・People in major eventsTu Ming-chengMinquan Police Box constable killed on duty
- 1987 to present・People in major eventsTu Yi-hsinFamily member of an officer killed in the Taijiang Boulevard police killings
- Tucheng Industrial ZoneUrban-planning industrial zone in Annan DistrictContains 1 items
- 1987 to present・Doctors, lawyers and other professionalsWu An-taiFirst-instance defense counsel in the Taijiang Boulevard case
- 1987 to present・Postwar officialsWu Shu-hsienCommissioned judge in the appeal of the Taijiang Boulevard police killing case
Reports that mention it
Hall of the Present6.7Everyday memories / Remembered eventsMain
Events Remembered in Tucheng
This page is not a set of crime statistics but what local people remember: on August 22, 2022, two police officers were killed near the intersection of Taijiang Boulevard Section 4 and Beishanwei 3rd Road.
Hall of Local Memory9.7Everyday memories / Remembered eventsMain
The 2022 Killing of Two Police Officers on Taijiang Boulevard
On August 22, 2022, Tu Ming-cheng (凃明誠) and Tsao Jui-chieh (曹瑞傑), officers of the Minquan Police Substation, Second Precinct, Tainan City Government Police Department, were killed near the intersection of Taijiang Boulevard Section 4 and Beishanwei 3rd Road in Annan District while tracing a stolen motorcycle. The defendant, Lin Hsin-wu (林信吾), was sentenced to death at first instance; the second-instance judgment is scheduled to be pronounced on December 18, 2026, and the case is not yet final.
Hall of Local Memory9.5Ecology / Species
The Bats of the Settlement and That Banyan Grove
On the road home from the Shengmu Temple, great numbers of bats come out at night to eat mosquitoes. They live in the banyan grove behind the temple, a grove that was later cut in two by Taijiang Boulevard (2014–2015) and partly felled, though the woods are still there.
Hall of Local Memory9.8Settlement / Roads and transportation
Tucheng Goes to Town: Haidian Road, Hewei, and Garden Night Market
When Tucheng people say they are "going into town," they mean a specific route: Anzhong Road, then Haidian Road, then across the Yanshui River Bridge. Until 2019 that bridge was only 18 meters wide, although the roads at both ends were 30 meters wide.
Hall of Local Memory9.9Everyday memories / Old trees
The Old Trees of Tucheng
Tainan City's register of protected old trees lists only 6 in Annan District, and only 2 in the five villages of Tucheng, both on Chengxi Street Section 2 in Chengnan Village. Yet a two-day walk around Tucheng on October 26 and 27, 2026 recorded more than thirty old-tree sites, numbered T1–T28, S1–S6, and C1, the great majority of them on no register at all.
Hall of Incense Festivals4.6Faith / Temple events
The Lantern Festival: Fireworks, the Spring Ox, and the Street Parade
Tucheng's Lantern Festival has two sets of protagonists: one is the aerial fireworks and beehive fireworks encircling the temple that officials and the media report on every year; the other is something only local people remember — schoolchildren led by their teachers to parade in front of the temple, and, after the fireworks, being unable to squeeze out of the crowds.
- Hall of the PresentHall front page: Hall of the Present