Siltation of the Luermen River

Official recordUnverifiedSecondhand account
1144

Verification status of the entries on this page

  • Verified
  • Partially verified
  • Not covered by sources
  • Verified: the source was found and checked
  • Partially verified: only part could be checked, or the check found the opposite
  • Not covered by sources: nothing found in currently available public records

Guided reading

Flow-training and dredging works awarded on 2024-12-24 for NT$43,688,000, fully subsidized by the Water Resources Agency; the channel depth is to be increased to 1.5 meters so that boats from Sicao Fishing Harbor can pass, and the dredged sediment is used for beach nourishment outside the Sicao seawall.R001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication.

Current status
The Tuchengzi Drain tide gate works began in mid-February 2026 and are expected to be completed before the 2027 flood season; the river-mouth flow-training contract was awarded at the end of 2024 R007SourcePress release of the Water Resources Bureau, Tainan City Government, 〈安南區土城仔排水防潮閘門治理工程與抽水設備說明〉[Explanation of the Annan District Tuchengzi Drain Tide Gate Works and Pumping Equipment] (NT$150 million subsidy approved by the Water Resources Agency; construction began in mid-February 2026, expected completion before the 2027 flood season; five-bay tide gate, each bay 4.2 m wide and 2.6 m high, with 2 pumping units of 4 CMS; box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; double-bay gate on the Shalunjiao middle drain; catchment ground elevation about 1.0–4.0 m, settlement roads mostly below 2.0 m); and the same bureau's 〈城西街一段側溝銜接城南路土城仔排水箱涵處抽水設備說明〉[Explanation of the Pumping Equipment Where the Side Ditch of Chengxi Street Section 1 Joins the Tuchengzi Drain Box Culvert at Chengnan Road]Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8807089Retrieved2026-10-27Snapshot timestamp—Official source. See also the side-ditch pumping equipment: https://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8585818 .R001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication.
Key figures
  • NT$43,688,000Flow-training and dredging contract awardR001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication.
  • 1.5 mTarget channel depthR002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19
  • 20,000–25,000 m³ per yearRoutine dredging volumeR004SourceRoutine dredging records of the Agriculture Bureau, Tainan City Government (臺南市政府農業局) (20,000–25,000 m³ per year; 11 times in ROC years 101–111 [2012–2022])Original URLhttps://agri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19Routine dredging and the 2024 flow-training works are matters of different orders and must not be described together as one.
  • NT$150 millionTide gate works subsidyR007SourcePress release of the Water Resources Bureau, Tainan City Government, 〈安南區土城仔排水防潮閘門治理工程與抽水設備說明〉[Explanation of the Annan District Tuchengzi Drain Tide Gate Works and Pumping Equipment] (NT$150 million subsidy approved by the Water Resources Agency; construction began in mid-February 2026, expected completion before the 2027 flood season; five-bay tide gate, each bay 4.2 m wide and 2.6 m high, with 2 pumping units of 4 CMS; box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; double-bay gate on the Shalunjiao middle drain; catchment ground elevation about 1.0–4.0 m, settlement roads mostly below 2.0 m); and the same bureau's 〈城西街一段側溝銜接城南路土城仔排水箱涵處抽水設備說明〉[Explanation of the Pumping Equipment Where the Side Ditch of Chengxi Street Section 1 Joins the Tuchengzi Drain Box Culvert at Chengnan Road]Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8807089Retrieved2026-10-27Snapshot timestamp(None, or not applicable)Official source. See also the side-ditch pumping equipment: https://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8585818 .
Evidence mix
Verification
  • ✓ Verified 11
  • ◑ Partially verified 4
  • ⊗ Not covered by sources 4
Source type
  • Official record 9
  • Unverified 2
✓ ◑ ⊗
  • ✓ Verified: the source was found and checked
  • ◑ Partially verified: only part could be checked, or the check found the opposite
  • ⊗ Not covered by sources: nothing found in currently available public records

Why it matters

The Luermen River is a channel that has to be cleared every year, and boats from Sicao Fishing Harbor depend on it to come and go R004SourceRoutine dredging records of the Agriculture Bureau, Tainan City Government (臺南市政府農業局) (20,000–25,000 m³ per year; 11 times in ROC years 101–111 [2012–2022])Original URLhttps://agri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19Routine dredging and the 2024 flow-training works are matters of different orders and must not be described together as one.R002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19. Its upstream catchment includes the Tuchengzi main drain: where Tucheng's rainwater goes and whether the river mouth gets a flow-training structure are two ends of the same drainage system R002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19R003SourceNotice of the 《鹿耳門排水系統用地範圍線圖》[Land Boundary Line Maps of the Luermen Drainage System] (2025-09-30, including 14 map sheets for the Tuchengzi Drain)Original URL—Retrieved2026-10-24Snapshot timestamp2026-10-19The upstream catchment includes the Tuchengzi main drain, the direct link between this page and the Tucheng settlement.. Most roads in the Tucheng settlement lie below 2.0 m, so at high summer tides the low-lying parts of Chengxi Street Section 1 risk seawater backflow and flooded roads R007SourcePress release of the Water Resources Bureau, Tainan City Government, 〈安南區土城仔排水防潮閘門治理工程與抽水設備說明〉[Explanation of the Annan District Tuchengzi Drain Tide Gate Works and Pumping Equipment] (NT$150 million subsidy approved by the Water Resources Agency; construction began in mid-February 2026, expected completion before the 2027 flood season; five-bay tide gate, each bay 4.2 m wide and 2.6 m high, with 2 pumping units of 4 CMS; box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; double-bay gate on the Shalunjiao middle drain; catchment ground elevation about 1.0–4.0 m, settlement roads mostly below 2.0 m); and the same bureau's 〈城西街一段側溝銜接城南路土城仔排水箱涵處抽水設備說明〉[Explanation of the Pumping Equipment Where the Side Ditch of Chengxi Street Section 1 Joins the Tuchengzi Drain Box Culvert at Chengnan Road]Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8807089Retrieved2026-10-27Snapshot timestamp—Official source. See also the side-ditch pumping equipment: https://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8585818 ..

Main actors

Central government 2

  • Water Resources Agency, MOEAFully subsidized the flow-training works; approved a NT$150 million tide gate subsidyR001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication.
  • Sixth River Management Branch, Water Resources Agency, MOEAPress releases on the flow-training worksR002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19

Local government 2

  • Water Resources Bureau, Tainan City GovernmentTuchengzi Drain improvement, regulation and tide gate worksR006SourcePress release of the Water Resources Bureau, Tainan City Government, 〈土城仔排水改建完成,水利局期能改善當地水患問題〉[Tuchengzi Drain Reconstruction Completed; Water Resources Bureau Hopes to Improve Local Flooding] (the 「土城仔排水改善工程」[Tuchengzi Drain Improvement Works] of the Luermen drainage system, 0K+000–0K+750, Chengnan Village; construction began December 2016 and was completed 2018-09-04, cost NT$91 million; channel widened from 10 m to 20 m, embankment raised to an elevation of 2.6 m, a 6 m flood-control road newly built on each bank)Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=607973Retrieved2026-10-27Snapshot timestamp(None, or not applicable)Official source.
  • Agriculture Bureau, Tainan City GovernmentRoutine dredging, 11 times in ROC years 101–111 (2012–2022)R004SourceRoutine dredging records of the Agriculture Bureau, Tainan City Government (臺南市政府農業局) (20,000–25,000 m³ per year; 11 times in ROC years 101–111 [2012–2022])Original URLhttps://agri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19Routine dredging and the 2024 flow-training works are matters of different orders and must not be described together as one.

Local users 1

  • Boats of Sicao Fishing HarborThe channel is deepened to 1.5 m for their passageR002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19

Turning points

  1. 2018-09-04Downstream Tuchengzi Drain improvement completed; channel widened to 20 mR006SourcePress release of the Water Resources Bureau, Tainan City Government, 〈土城仔排水改建完成,水利局期能改善當地水患問題〉[Tuchengzi Drain Reconstruction Completed; Water Resources Bureau Hopes to Improve Local Flooding] (the 「土城仔排水改善工程」[Tuchengzi Drain Improvement Works] of the Luermen drainage system, 0K+000–0K+750, Chengnan Village; construction began December 2016 and was completed 2018-09-04, cost NT$91 million; channel widened from 10 m to 20 m, embankment raised to an elevation of 2.6 m, a 6 m flood-control road newly built on each bank)Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=607973Retrieved2026-10-27Snapshot timestamp(None, or not applicable)Official source.
  2. 2024-12-24Luermen River flow-training and dredging contract awardedR001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication.
  3. 2025-07-16Public hearing on the Tuchengzi Drain 1K+720 to 2K+820 regulation worksR008SourceWater Resources Bureau, Tainan City Government, 〈鹿耳門排水系統-土城仔排水1K+720~2K+820治理工程公聽會公告〉[Notice of Public Hearing on the Luermen Drainage System – Tuchengzi Drain 1K+720–2K+820 Remediation Works] (held at the Annan District Office [安南區公所] on 2025-07-16)Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5239&s=8759887Retrieved2026-10-27Snapshot timestamp(None, or not applicable)Official source.
  4. 2025-09-30Land-use boundary maps of the Luermen drainage system announcedR003SourceNotice of the 《鹿耳門排水系統用地範圍線圖》[Land Boundary Line Maps of the Luermen Drainage System] (2025-09-30, including 14 map sheets for the Tuchengzi Drain)Original URL(None, or not applicable)Retrieved2026-10-24Snapshot timestamp2026-10-19The upstream catchment includes the Tuchengzi main drain, the direct link between this page and the Tucheng settlement.
  5. 2026Tuchengzi Drain tide gate works beginR007SourcePress release of the Water Resources Bureau, Tainan City Government, 〈安南區土城仔排水防潮閘門治理工程與抽水設備說明〉[Explanation of the Annan District Tuchengzi Drain Tide Gate Works and Pumping Equipment] (NT$150 million subsidy approved by the Water Resources Agency; construction began in mid-February 2026, expected completion before the 2027 flood season; five-bay tide gate, each bay 4.2 m wide and 2.6 m high, with 2 pumping units of 4 CMS; box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; double-bay gate on the Shalunjiao middle drain; catchment ground elevation about 1.0–4.0 m, settlement roads mostly below 2.0 m); and the same bureau's 〈城西街一段側溝銜接城南路土城仔排水箱涵處抽水設備說明〉[Explanation of the Pumping Equipment Where the Side Ditch of Chengxi Street Section 1 Joins the Tuchengzi Drain Box Culvert at Chengnan Road]Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8807089Retrieved2026-10-27Snapshot timestamp(None, or not applicable)Official source. See also the side-ditch pumping equipment: https://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8585818 .

Full recordBelow is the item-by-item record; every item cites its source.

What it is

The siltation of the Luermen River (鹿耳門溪) is not a single event but a channel that has to be cleared every year; the works awarded at the end of 2024 placed a fixed flow-training structure at the river mouth for the first time.

Flow-training and dredging works

The contract was awarded on 2024-12-24 for NT$43,688,000, against a budget of NT$48.5 million, fully subsidized by the Water Resources Agency, MOEA (經濟部水利署) R001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication.. Official record The method is a 150-meter flow-training structure on concrete foundation piles driven by jetting; the aim is to increase the channel depth to 1.5 meters so that boats from Sicao (四草) Fishing Harbor can pass, and the dredged sediment is used for beach nourishment outside the Sicao seawall R002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19.

The channel of the Luermen River and the mudflats on both banks; the water is broad and slow, with the horizon toward the river mouth in the distance.
The channel of the Luermen River and the mudflats on both banks; the water is broad and slow, with the horizon toward the river mouth in the distance.Pbdragonwang/Wikimedia Commons · CC BY-SA 4.0 · Annan District, Tainan City

Routine dredging

Before the flow-training structure, the Luermen River had always been kept open by routine dredging. The records of the Agriculture Bureau, Tainan City Government (臺南市政府農業局) show 20,000 to 25,000 cubic meters a year, 11 times in all between ROC years 101 and 111 (2012–2022) R004SourceRoutine dredging records of the Agriculture Bureau, Tainan City Government (臺南市政府農業局) (20,000–25,000 m³ per year; 11 times in ROC years 101–111 [2012–2022])Original URLhttps://agri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19Routine dredging and the 2024 flow-training works are matters of different orders and must not be described together as one.. Official record Routine dredging and the 2024 flow-training works are matters of different orders: the former is maintenance, while the latter adds a fixed structure at the river mouth to change the flow.

The Tuchengzi main drain upstream

The upstream catchment of the Luermen River includes the Tuchengzi (土城仔) main drain R002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19. The Land Boundary Line Maps of the Luermen Drainage System (《鹿耳門排水系統用地範圍線圖》) announced on 2025-09-30 include 14 map sheets for the Tuchengzi Drain R003SourceNotice of the 《鹿耳門排水系統用地範圍線圖》[Land Boundary Line Maps of the Luermen Drainage System] (2025-09-30, including 14 map sheets for the Tuchengzi Drain)Original URL—Retrieved2026-10-24Snapshot timestamp2026-10-19The upstream catchment includes the Tuchengzi main drain, the direct link between this page and the Tucheng settlement.. Official record Where Tucheng's rainwater goes and whether the river mouth should be trained are the two ends of the same drainage system. This page can also be read alongside 6.6: this river is at the same time the axis of Taijiang National Park's (台江國家公園) "General Control Area 5 – Luermen River Riparian Zone" (「管(五)鹿耳門溪沿岸一般管制區」), and in 6.2 it is the channel downstream of the Taiwan Alkali Anshun Plant (台鹼安順廠) where sediment is monitored.

The Tuchengzi Drain

MoreLess

What Tucheng people call the "Tucheng main drain" (「土城大排」) is legally named the "Tuchengzi Drain" (「土城仔排水」) and belongs to the Luermen drainage system. According to the Executive Yuan Gazette's notice table of start and end points of regional drains, it begins at its confluence with the Luermen River drain and ends at Lane 735, Chengbei Road (城北路) (Shalun Village [沙崙里]); in the same table, the "Zhufagang Drainage No. 1" (「竹筏港之一排水」) ends at an unnamed bridge in Qingcao Village (青草里) R005SourceExecutive Yuan Gazette Online (行政院公報資訊網), 〈臺南市區域排水起訖點公告表〉[Notice Table of Start and End Points of Regional Drains in Tainan City] (Tuchengzi Drain: starting point at the confluence with the Luermen River drain, end point at Lane 735, Chengbei Road [Shalun Village]; Zhufagang Drainage No. 1: end point at an unnamed bridge [Qingcao Village])Original URLhttps://gazette.nat.gov.tw/EG_FileManager/eguploadpub/eg011220/ch04/type3/gov31/num2/Eg.htmRetrieved2026-10-27Snapshot timestamp—Official source.. Official record

The downstream section was done first: the "Tuchengzi Drain Improvement Works" (「土城仔排水改善工程」) of the Luermen drainage system (0K+000 to 0K+750, Chengnan Village [城南里], from the Luermen River to an unnamed bridge on Anqing Road Section 1 [安清路一段]) began in December 2016 and were completed on 2018-09-04 at a cost of NT$91 million; the channel was widened from 10 meters to 20 meters, the embankment raised to an elevation of 2.6 meters, and a 6-meter-wide flood-control road newly built on each bank R006SourcePress release of the Water Resources Bureau, Tainan City Government, 〈土城仔排水改建完成,水利局期能改善當地水患問題〉[Tuchengzi Drain Reconstruction Completed; Water Resources Bureau Hopes to Improve Local Flooding] (the 「土城仔排水改善工程」[Tuchengzi Drain Improvement Works] of the Luermen drainage system, 0K+000–0K+750, Chengnan Village; construction began December 2016 and was completed 2018-09-04, cost NT$91 million; channel widened from 10 m to 20 m, embankment raised to an elevation of 2.6 m, a 6 m flood-control road newly built on each bank)Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=607973Retrieved2026-10-27Snapshot timestamp—Official source.. Official record The middle and upper sections then went through the procedures: a public hearing on the "Tuchengzi Drain 1K+720 to 2K+820 Remediation Works" (「土城仔排水 1K+720 至 2K+820 治理工程」) was held at the Annan District Office (安南區公所) on 2025-07-16 R008SourceWater Resources Bureau, Tainan City Government, 〈鹿耳門排水系統-土城仔排水1K+720~2K+820治理工程公聽會公告〉[Notice of Public Hearing on the Luermen Drainage System – Tuchengzi Drain 1K+720–2K+820 Remediation Works] (held at the Annan District Office [安南區公所] on 2025-07-16)Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5239&s=8759887Retrieved2026-10-27Snapshot timestamp—Official source.. Official record

Further downstream is the gate at the outlet: the "Annan District Tuchengzi Drain Tide Gate Works" (「安南區土城仔排水防潮閘門治理工程」), with a NT$150 million subsidy approved by the Water Resources Agency, MOEA, began in mid-February 2026 and is expected to be completed before the 2027 flood season — a five-bay tide gate (each bay 4.2 meters wide and 2.6 meters high) and 2 pumping units of 4 CMS on the Tuchengzi Drain; a box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; and a double-bay gate on the Shalunjiao (沙崙角) middle drain R007SourcePress release of the Water Resources Bureau, Tainan City Government, 〈安南區土城仔排水防潮閘門治理工程與抽水設備說明〉[Explanation of the Annan District Tuchengzi Drain Tide Gate Works and Pumping Equipment] (NT$150 million subsidy approved by the Water Resources Agency; construction began in mid-February 2026, expected completion before the 2027 flood season; five-bay tide gate, each bay 4.2 m wide and 2.6 m high, with 2 pumping units of 4 CMS; box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; double-bay gate on the Shalunjiao middle drain; catchment ground elevation about 1.0–4.0 m, settlement roads mostly below 2.0 m); and the same bureau's 〈城西街一段側溝銜接城南路土城仔排水箱涵處抽水設備說明〉[Explanation of the Pumping Equipment Where the Side Ditch of Chengxi Street Section 1 Joins the Tuchengzi Drain Box Culvert at Chengnan Road]Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8807089Retrieved2026-10-27Snapshot timestamp—Official source. See also the side-ditch pumping equipment: https://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8585818 .. Official record The Water Resources Bureau explains the flooding mechanism as follows: the catchments of the Tuchengzi Drain and the Tuchengzi No. 1-2 Drain have ground elevations of about 1.0 to 4.0 meters, and the main settlement roads are mostly below 2.0 meters, so when summer tides are high the low-lying parts of the Tuchengzi settlement (Chengxi Street Section 1 [城西街一段]) are at risk of seawater backflow and flooded roads; pumping equipment has already been installed where the side ditch of Chengxi Street Section 1 joins the box culvert at Chengnan Road R007SourcePress release of the Water Resources Bureau, Tainan City Government, 〈安南區土城仔排水防潮閘門治理工程與抽水設備說明〉[Explanation of the Annan District Tuchengzi Drain Tide Gate Works and Pumping Equipment] (NT$150 million subsidy approved by the Water Resources Agency; construction began in mid-February 2026, expected completion before the 2027 flood season; five-bay tide gate, each bay 4.2 m wide and 2.6 m high, with 2 pumping units of 4 CMS; box culvert, pumping platform, and gate on the Tuchengzi No. 1-2 Drain; double-bay gate on the Shalunjiao middle drain; catchment ground elevation about 1.0–4.0 m, settlement roads mostly below 2.0 m); and the same bureau's 〈城西街一段側溝銜接城南路土城仔排水箱涵處抽水設備說明〉[Explanation of the Pumping Equipment Where the Side Ditch of Chengxi Street Section 1 Joins the Tuchengzi Drain Box Culvert at Chengnan Road]Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8807089Retrieved2026-10-27Snapshot timestamp—Official source. See also the side-ditch pumping equipment: https://wrb1.tainan.gov.tw/News_Content.aspx?n=5234&s=8585818 .. Official record

None of the 17 detention ponds under the Tainan City Water Resources Bureau (register as of 2022-09-16) lies in the Tuchengzi Drain or Zhufagang Canal (竹筏港溪) basin; the three in Annan District (安南區) are Lide Detention Pond (1), Haiwei (海尾), and Benyuanliao (本淵寮) R009SourceTainan City Council (臺南市議會), 〈滯洪池管理維護專案報告名冊〉[Register for the Special Report on the Management and Maintenance of Detention Ponds] (17 detention ponds under the Water Resources Bureau as of 2022-09-16; those in Annan District are Lide Detention Pond (1), Haiwei, and Benyuanliao); Water Resources Agency, MOEA, 《臺南市水災保全計畫》[Tainan City Flood Protection Plan]; Water Resources Agency e-newsletter, 〈海東D抽水站及本淵寮滯洪池聯合操作工程完工〉[Completion of the Joint Operation Works for the Haidong D Pumping Station and Benyuanliao Detention Pond]Original URLhttps://bill.tncc.gov.tw/NoPaperMeeting_TNCC/Api/WEB017_DownloadFile.ashx?attno=34040e0f-c989-4f0a-b157-64e66284f7c9Retrieved2026-10-27Snapshot timestamp—Official source. The correct wording is "not listed in the register," not "Tucheng has none.". Official record

Differing accounts

  1. UnverifiedThe amount for the flow-training and dredging works:
    • Award amount NT$43,688,000 R001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication..
    • Budget NT$48.5 million R001SourceAward notice on the Government e-Procurement System (政府電子採購網) (contract awarded 2024-12-24 for NT$43,688,000; budget NT$48.5 million, fully subsidized by the Water Resources Agency [水利署])Original URLhttps://web.pcc.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19A press release cites an approved amount of NT$54.8 million; this differs from both the award amount and the budget. The three figures are presented side by side without adjudication..
    • A press release cites an approved amount of NT$54.8 million R002SourcePress releases of the Water Resources Bureau, Tainan City Government (臺南市政府水利局) and the Sixth River Management Branch, Water Resources Agency, MOEA (經濟部水利署第六河川分署) (flow-training structure 150 m long, concrete foundation piles driven by jetting; channel depth increased to 1.5 m for boats from Sicao Fishing Harbor; dredged sediment used for beach nourishment outside the Sicao seawall)Original URLhttps://www.wri.tainan.gov.tw/Retrieved2026-10-24Snapshot timestamp2026-10-19.
  2. UnverifiedThe length of the Tuchengzi Drain:
    • The draft gazetteer of Huweiliao (虎尾寮庄志草本) gives the Tucheng main drain a 「全長 1.7 公里」 ("total length of 1.7 kilometers") R005SourceExecutive Yuan Gazette Online (行政院公報資訊網), 〈臺南市區域排水起訖點公告表〉[Notice Table of Start and End Points of Regional Drains in Tainan City] (Tuchengzi Drain: starting point at the confluence with the Luermen River drain, end point at Lane 735, Chengbei Road [Shalun Village]; Zhufagang Drainage No. 1: end point at an unnamed bridge [Qingcao Village])Original URLhttps://gazette.nat.gov.tw/EG_FileManager/eguploadpub/eg011220/ch04/type3/gov31/num2/Eg.htmRetrieved2026-10-27Snapshot timestamp—Official source..
    • The remediation chainage extends at least to 2K+820 R008SourceWater Resources Bureau, Tainan City Government, 〈鹿耳門排水系統-土城仔排水1K+720~2K+820治理工程公聽會公告〉[Notice of Public Hearing on the Luermen Drainage System – Tuchengzi Drain 1K+720–2K+820 Remediation Works] (held at the Annan District Office [安南區公所] on 2025-07-16)Original URLhttps://wrb1.tainan.gov.tw/News_Content.aspx?n=5239&s=8759887Retrieved2026-10-27Snapshot timestamp—Official source..