Annan District Fishery–Solar Co-location Application and Review Process

Official record
400

Verification status of the entries on this page

  • Verified
  • Partially verified
  • Not covered by sources
  • Verified: the source was found and checked
  • Partially verified: only part could be checked, or the check found the opposite
  • Not covered by sources: nothing found in currently available public records

The Annan District fishery–solar co-location application and review process is the application quick guide and review standard operating procedure for fishery–solar co-location announced by the Annan District Office, Tainan City, on its "Sunshine Green Energy Zone" page.R001Source臺南市安南區公所 [Annan District Office, Tainan City],漁電共生申請懶人包、審核標準作業程序(SOP)全攻略 [Quick guide to fishery–solar applications and complete guide to the review standard operating procedure (SOP)]Original URLhttps://www.annan.gov.tw/News_Content.aspx?n=47260&s=8808008Retrieved2026-11-06Snapshot timestamp(None, or not applicable)Official announcement and attached PDF

Category
Terms
Related reports
1 reports
Also known as
安南區陽光綠能專區、漁電共生申請懶人包、Annan Sunshine Green Energy Zone、Fishery–Solar Application Quick Guide
Related subpages
6.4

The Annan District fishery–solar co-location application and review process is the quick guide to fishery–solar applications and the review standard operating procedure (SOP) announced by the Annan District Office, Tainan City, on its "Sunshine Green Energy Zone" page R001Source臺南市安南區公所 [Annan District Office, Tainan City],漁電共生申請懶人包、審核標準作業程序(SOP)全攻略 [Quick guide to fishery–solar applications and complete guide to the review standard operating procedure (SOP)]Original URLhttps://www.annan.gov.tw/News_Content.aspx?n=47260&s=8808008Retrieved2026-11-06Snapshot timestamp—Official announcement and attached PDF. Official record Applications have four stages, and the stated principles include a coverage ratio below 40% (outdoor type), safeguarding actual aquaculture, priority for the work rights of the original fishers, and ecological protection; the six-step review SOP calls for maintaining a set proportion of output (for example 70% or more) and avoiding important wetlands and ecological protection areas R001Source臺南市安南區公所 [Annan District Office, Tainan City],漁電共生申請懶人包、審核標準作業程序(SOP)全攻略 [Quick guide to fishery–solar applications and complete guide to the review standard operating procedure (SOP)]Original URLhttps://www.annan.gov.tw/News_Content.aspx?n=47260&s=8808008Retrieved2026-11-06Snapshot timestamp—Official announcement and attached PDF.

Application procedure

  1. Preparation and assessment (landowner and operator sign a contract; environmental and social checklist).
  2. Administrative application, stage 1: permit for permitted use of agricultural facilities (district office, Agriculture Bureau).
  3. Administrative application, stage 2: permit for permitted use of green-energy facilities (completion and aquaculture-fact inspection).
  4. Energy application and grid connection (approval of filing, Taipower grid connection).

Application principles

The principles listed in the quick guide R001Source臺南市安南區公所 [Annan District Office, Tainan City],漁電共生申請懶人包、審核標準作業程序(SOP)全攻略 [Quick guide to fishery–solar applications and complete guide to the review standard operating procedure (SOP)]Original URLhttps://www.annan.gov.tw/News_Content.aspx?n=47260&s=8808008Retrieved2026-11-06Snapshot timestamp—Official announcement and attached PDF: Official record

  1. A coverage ratio below 40% (outdoor type).
  2. Safeguarding actual aquaculture (periodic inspection by the city government).
  3. Priority for the work rights of the original fishers.
  4. Ecological protection (Annan District wetlands and waterbirds).

Review standard operating procedure

Six steps: Official record

  1. Preparation and site assessment.
  2. Application for permitted use of agricultural facilities.
  3. Review of the renewable-energy facility business plan.
  4. Application for miscellaneous permits and building permits.
  5. Completion inspection and application for an operating license.
  6. Ongoing operation management and output reporting.

Among the requirements are maintaining a set proportion of output (for example 70% or more) and avoiding important wetlands and ecological protection areas R001Source臺南市安南區公所 [Annan District Office, Tainan City],漁電共生申請懶人包、審核標準作業程序(SOP)全攻略 [Quick guide to fishery–solar applications and complete guide to the review standard operating procedure (SOP)]Original URLhttps://www.annan.gov.tw/News_Content.aspx?n=47260&s=8808008Retrieved2026-11-06Snapshot timestamp—Official announcement and attached PDF.

Progress disclosure

The district office also maintains a dashboard of "fishery–solar review cases and progress" (a dynamic Looker Studio page). Unverified

See also

Reports that mention it

Hall of the Present6.4Present conditions and institutions / Industrial parks and pollution

Fishery–Solar Co-location and Solar Power

Milkfish farming area has shrunk by a third in ten years, 330 hectares of fish farm ponds sit on illegal land-use categories, and no solar panels are to go west of Provincial Highway 61. Yet not one of the fishery–solar and ground-mounted solar projects in this area has an EIA case number — not because environmental impact assessment failed to do its job, but because the law at the time did not require one.